Notes 8/2/17

CALSTATE weekly call

Wednesday, August 2, 20174

11:00 AM

 

~~START RECORDING~~ 

 

  1. Staff availability
  • July 28 - Aug 4: Laurie out
  • July 31 - Aug 2: Svetlana out; Brandon out (LibTech)
  • July 31 - Aug 4: David Walker out (LibTech)
  • Aug 1-2: Jim out (onsite w/ customer)

 

  1. Project milestones
  • Switch To Support meeting August 9 –  led by Brian Noone, Sr. Support Manager
  • After this meeting:
    • Implementation project will be officially complete.
    • Basecamp will be set to read-only mode.
    • Existing cases owned by the ExL Project Team will stay there until they are either closed or sent to Tier 2 Support or Development for resolution.
    • All new cases will go to the Support Team rather than the ExL Project Team.

 

  1. Primo status
  • Report new issues and questions via Salesforce; internal CSU discussions to Slack / listservs.
  • Sandbox repopulation in progress
  • NR changes and renorms – next renorm scheduled Aug 4 (through weekend)
  • Primo August release scheduled for delivery – Sandbox Aug 6; Prod Aug 13
    • See August 2017 Release Notes; several New UI features added
  • Ongoing publishing cycle will resume normal daily operations after sandbox repopulation
  • Google Scholar cases – some resolved, some pending next Google Scholar update cycle

 

 

  1. Alma status
  • Report new issues and questions via Salesforce; internal CSU discussions to Slack / listservs.

 

 

 

    V.         Thank you!

 

 


 

Chat transcript

from Mike to everyone:

would it be helpful to have our local operational team watch this as a group?

from Mike to everyone:

sounds good

from Mark B (Los Angeles) to everyone:

Thank you again, to you all at Ex Libris

 

from A Hor (Stanislaus):

Thank you, Dolph, for your leadership.  Your team is great!

from Alice Kawakami -CSU to everyone:

thanks everyone!