Final Status Report

Date

5/4/17

Working Group

Systems & Development

Task Force
Self-Check / SIP2 / Stunnel
Report Summary

Six of eight campuses that were planning on going live with self-check successfully tested and have operational machines. Five of these campuses reported feedback in a self-check testing form available on Confluence (Testing Status for Self-Check). The two remaining campuses that are planning on going live with self-check have communicated that they intend to test and implement self-check with launch. San Luis Obispo tested and needs to troubleshoot. Channel Islands is planning on testing in the next few weeks.

The status of major milestones have been marked as completed, despite two campuses that have not yet tested but are planning on going live with self-check.






Description



Action ItemsNone.