Group 2: Monterey Bay, Sonoma, Fullerton, Channel Islands, Los Angeles, Long Beach, Pomona |
|
|
|
|
|
Week Of | Activities | Owners | Downtime |
4/9/2017 | CSU updates Alma Health Checklist on Basecamp; CSU downloads and begins prep of Migration Form, Field Mapping Form (III), P2E, 360 Forms, Delivered Files List; ExL Project Team answers questions and assists with checklist issues | all | n/a |
4/16/2017 | CSU continues prep of Migration Form, Field Mapping Form, P2E, 360 Forms, Delivered Files List; ExL sending feedback & answering questions from forms and health checklist | all | n/a |
4/23/2017 | DRAFT Migration Form, Field Mapping Form, P2E, 360 Forms, Delivered Files List posted to SF case for ExL Project & Migration Teams review | all | n/a |
4/30/2017 | Final revisions to Migration Form, Field Mapping Form, P2E, 360 Forms, Delivered Files List updated to SF case; ExL sending feedback & answering questions | all | Â |
5/7/2017 | FINAL Migration Form, Field Mapping Form, P2E, 360 Forms, Delivered Files List due via SF cases for Migration Team Review | all | Â |
5/14/2017 | Data files due on ExL FTP server by end of week | all | III + Voy tech freeze (no further Cat + Acq); Alma config freeze begins |
5/21/2017 | Migration activities | ExL Migration | Â |
5/28/2017 | Migration activities | ExL Migration | Â |
6/4/2017 | ExL Project Team checks migrated data | ExL PS | Â |
6/11/2017 | ExL Project Team delivers cutover environment; campuses + CO check data; data publishing to Primo is started; CSU confirms acceptance of Alma data migration; CSU delivers final fulfillment data (loans, patrons, requests) | all | Primo config freeze begins; Alma config freeze ends |
6/18/2017 | Primo publishing completes; ExL Migration loads fulfillment data; ExL Project Team checks and delivers Alma & Primo to CSU; CSU checks fulfillment data & Primo and confirms acceptance; ExL turns on job schedule and unscrubs e-mail; GO LIVE DATE IS 6/20 -- each campus notifies CSU and ExL when live work has begun | all | III + Voy circ freeze (no further activity in III, Voy, or 360; use Alma Offline Circ - 2 days); Primo config freeze ends |
6/25/2017 | CSU updates Alma Health Checklist; ExL Project Team answers questions and assists with checklist issues | all | Â |
7/2/2017 | Planning for Switch To Support (est 7/31) | all | Â |