ULMS Project Timeline (graphical)

Oct2015NovDecJan2016FebMarAprMayJunJulAugSepOctNovDecJan2017FebMarAprMayJunJulOnsite Kickoff MeetingAccess to SandboxCampus Implementatio…Access to Alma/Prim…In-Person Trainin…In-Person Trainin…Go-Live BeginsAlma Health CheckHandoff to Support
Planning
Define
Build
Deploy

Project Plan

Project Status Calls

Web-Based Alma Training

Vanguard institutions & NZ test load/config

Primo Initial Config & delivery

Workflow & Data Review

Web-based Alma Training

Provide config/data migration inputs to Ex Libris

Test Load and Configuration

3rd Party Integration

Workflow & Data Review

Monitoring Go Live Readiness

Resource Sharing Configuration

Web-Based Certification Training

Library Staff Training

Cutover

Sacramento and San Marcos linked to NZ