Overall Status

Status
colourBlue
titleIn-Progress
 

Major Milestones

 

StageComplete ByStatus
Meet with CO CMS and Identity Management group to discuss project

 

Status
colourGreen
titleCompleted

Meet with vanguard campuses (Fresno, Fullerton, Northridge) to discuss project

 

Status
colourGreen
titleCompleted

Vanguard campuses tweak existing process to accommodate Alma

 

Status
colourGreen
titleCompleted

Review survey of libraries' needs regarding parton load

 

Status
colourGreen
titleCompleted

Deliver draft requirements document and sample code from vanguard campuses to CMS

 

Status
colourGreen
titleCompleted

Create Access Services taskforce to standardize patron types and expiry date

 

Status
colourGreen
titleCompleted

Final requirements document delivered to CO CMS

 

Status
colourGreen
titleCompleted

CO CMS develops initial export process

 

Status
colourBlue
titleIn-Progress
Begin testing of CO-developed patron extract with initial test group (= vanguard) campuses

 

Status
colourBlue
titleIn-Progress
Testing and feedback

 

Status
colourRed
titleNot started

CMS Development updates 

 

Status
colourRed
titleNot started

Campus round 2 testing

 

Status
colourRed
titleNot started

CMS final development

 

Status
colourRed
titleNot started

Project delivered in MP 24 

 

Status
colourRed
titleNot started

Project Team

Why are we doing this?

Staff need to be able to login to Alma and end-users need to be able to login to Primo to perform tasks.  Adopting a systemwide approach allows us to streamline the process for setting-up authentication.  It also allows us to coordinate this work with the related task of automating the loading of patron data from PeopleSoft to Alma.

Documentation:

Meeting Notes: