titleEnablement Phase (April 1926- May 10)

“In this phase, we move your activations from your Primo Central institutional profile to Alma and enable all CDI functionality on Alma.” in the PC to CDI Activation Report  “that is viewable in your Alma environment: 1. A list of all your active collections in your Primo Central institutional profile. 2. The actions that were performed on each collection that was processed in the move to Alma.” 

  1. Re-Check Activations

    1. Check out the PC to Alma Activation report 

      1. Resources>Advanced Tools>PC to CDI Activation Reports

      2. Explore CDI activation in Alma

      3. Keep in mind: Known CDI Issues and Gaps

  2. Read the Rollout Plan for Alma Customers

    1. Note: “All Primo Central activations will be activated in your Alma production environment for search as they were in your Primo Central institutional profile at the time of the move. Collections that are set to full text available at the collection level in Primo Central, but are not active for full text in Alma will receive the following status: Activated for CDI only. You can track those activations in the move report. Any changes that you make to your Primo Central institutional profile after the move will not automatically appear in Alma and will have to be added manually. However, many of those activations may already occur in Alma as part of your activation flows.

  3. Assign the CDI Inventory Operator role to the appropriate staff. Ex Libris recommends combining the CDI Inventory Operator with the existing Electronic Collection Inventory Operator role.

  4.  “Publishing to CDI will be enabled, and CDI will be localized with your Alma settings. Activation changes from Alma (including the activations from the move from Primo Central) take between 24 and 48 hours to take effect.”

    1. As Brandon said, enablement, “should have no impact on current operations using PCI” however this does mean that both the PCI and CDI will have to be maintained simultaneously until the migration.

  5. Currently all institutions in a consortium (connected to one Alma network) need to be on the same setting. FullyFlexible is the default but can move to EasyActive as a consortium.

    1. If we remain on Fully Flexible then we will need to maintain alternative coverage. If we move to EasyActive then alternative coverage is automatically maintained.

      1. Notes on Alternative Coverage

  6. If an individual campus would like to move to EasyActive (works similar to Summon) please contact Jessica Hartwigsen. This is not an option yet but we can submit a request to Ex Libris to see if this is possible.

  1. Submit feedback here. If folks ask cdi_info@exlibrisgroup.com and get an answer that you’d like to be placed on the wiki, please use the form or email one of the group members.

...

Milestone

Deadline

Review PCI Collections

March 6, 2020

Check Activation Report

March 17, 2020 -

CSU enablement

April 1926, 2020-

Assign CDI Inventory Operator

April 1926, 2020 -

Tech User Testing

April 1926, 2020 -

CSU Wide User Testing

May 11, 2020 -

Go Live

TBA

...