March 2016

Full implementation kickoff meeting

 

Onsite meeting including analysis sessions

 

Production environment provisioned for all member institutions

 

CSU reviews recorded training (continuation and/or broader audience)

 

Go live readiness checklist introduced (monitored on an ongoing

 

basis for remainder of project)

April 2016

Preparation for full test load/data migration to production environment
– all member institutions and network zone

May 2016

Full test load/data migration to production environment begins – all

 

member institutions and network zone

 

Initial Alma configuration begins – all member institutions and network

 

zone

June 2016

Begin 3rd party integrations

July 2016

Full test load/data migration to production environment delivered to

 

CSU – all member institutions and network zone (early July)

 

Initial Alma configuration delivered to CSU – all member institutions

 

and network zone (early July)

 

Full Primo configuration and data load delivered to CSU – all member

 

institutions (late July)

August 2016

Workflow and data review by CSU (ongoing for remainder of project)

 

Onsite Workshop (1 of 2)

 

Configuration and integration refinements (ongoing for remainder of

 

project)

 

Planning for migration refinements (ongoing until start of cutover)

September 2016

Resource sharing set up

 

Prepare for San Marcos and Sacramento integration into CSU lending

 

environment

November 2016

Certification training

December 2016‐ January 2017

Winter break

January 2017

Onsite Workshop (2 of 2)

March 2017

Library staff training

April-May 2017

Cutover load/data migration begins – all member institutions

 

Library staff training

May

June 2017

Go Live with Alma and Primo

June 2017

Relink existing Alma sites (San Marcos and Sacramento) to the CSU

 

network zone.
 

June-July 2017

Alma health check

July

August 2017

Switch from implementation to ongoing support

...