Table of Contents | ||||
---|---|---|---|---|
|
Upon contract |
signature | CSU project manager, implementation team, institution contacts, and IT |
| resources established |
|
Ex Libris implementation team allocated |
|
Communication plan developed | |
|
Detailed implementation plan developed | |
|
"Getting Ready" kit review, including data preparation |
October2015
October 2015 | Planning phase ‐ kickoff meeting |
|
Production environment provisioned to be populated with the data |
|
from 3 "vanguard" member institutions (to be used for planning) |
|
Standard sandbox environment provisioned (to be used for training) | |
|
CSU reviews recorded training | |
|
Weekly project status/functional Q&A sessions between CSU and Ex | |
|
Libris implementation teams begin and continue throughout project |
November‐December 2015 |
Consultative review of Alma data model, workflows, migration and implementation details, to facilitate shared practices and policy planning | |
late December 2015‐ |
January 2016 | Winter break |
January 2016
| Initial Alma test load/data migration to production environment with |
| data from 3 "vanguard" member institutions and network zone begins |
|
Initial Alma configuration for 3 "vanguard" member institutions and |
| network zone begins |
late January‐February 2016 |
Initial Alma test load/data migration to production environment for 3 |
| "vanguard" member institutions and network zone delivered to CSU |
|
Initial Alma configuration for 3 "vanguard" member institutions and |
| network zone delivered to CSU Initial Primo configuration and data load |
| delivered for 3 "vanguard" member institutions |
February 2016 |
Workflow and data review by CSU | |
|
Configuration refinements | |
|
Planning for migration refinements |
March 2016 |
Full |
implementation kickoff meeting |
| Onsite meeting including analysis sessions |
|
Production environment provisioned for all member institutions |
|
CSU reviews recorded training (continuation and/or broader audience) |
| Go live readiness checklist introduced (monitored on an ongoing |
|
basis for remainder of project) |
April 2016 |
Preparation for full test load/data migration to production environment |
May 2016 |
Full test load/data migration to production environment begins – all |
| member institutions and network zone |
|
Initial Alma configuration begins – all member institutions and network |
|
zone |
June 2016 |
Begin 3rd party integrations |
July 2016 |
Full test load/data migration to production environment delivered to |
| CSU – all member institutions and network zone (early July) |
|
Initial Alma configuration delivered to CSU – all member institutions |
|
and network zone (early July) |
|
Full Primo configuration and data load delivered to CSU – all member |
|
institutions (late July) |
August 2016 |
Workflow and data review by CSU (ongoing for remainder of project) |
|
Onsite Workshop (1 of 2) |
|
Configuration and integration refinements (ongoing for remainder of | |
|
project) |
|
Planning for migration refinements (ongoing until start of cutover) |
September 2016 |
Resource sharing set up |
|
Prepare for San Marcos and Sacramento integration into CSU lending | |
|
environment |
November 2016 |
Certification training |
December 2016‐ January 2017 |
Winter break |
January 2017 |
Onsite Workshop (2 of 2) |
March 2017 |
Library staff training |
April-May 2017 |
Cutover load/data migration begins – all member institutions |
|
Library staff training |
June 2017 |
Go Live with Alma and Primo |
June 2017
Relink existing Alma sites (San Marcos and Sacramento) to the CSU |
network zone. |
June-July 2017 | Alma health check |
August 2017 |
Switch from implementation to ongoing support |