Project Owner: David Walker

Overall Status

Status
colourBlue
titleIn-Progress
 

Webinars

Introduction to Primo Central with Xerxes, March 18, 2016

Follow-up Q&A session, April 8, 2016

Second follow-up Q&A session, May 13, 2016

Major Milestones

StageComplete ByStatus
Primo Central instances provisioned by Ex Libris
 

Status
colourGreen
titleCompleted

Initial integration of PCI into Xerxes

 

Status
colourGreen
titleCompleted

Webinars and training for CSU staff

 

Status
colourGreen
titleCompleted

Final bug fixes and refinements to facets

 

Status
colourBlue
titleIn progress

 

Go-live calendar

CampusDateStatus
Maritime
 

Status
colourGreen
titleCompleted

San Diego

 

Status
colourGreen
titleCompleted

Sonoma

 

 

Status
colourGreen
titleCompleted
Fullerton

 

Status
colourGreen
titleCompleted

Fresno

 

Status
colourGreen
titleCompleted

San Francisco

 

Status
colourGreen
titleCompleted

East Bay

 

Status
colourGreen
titleCompleted

San Luis Obispo

 

Status
colourGreen
titleCompleted

Pomona

 

Status
colourGreen
titleCompleted

San Bernardino

 

 

Status
colourGreen
titleCompleted

All other campuses

 

 

Why are we doing this?

Integrating Primo Central into Xerxes a year before going live with Primo allows us to end our Summon contract early, saving the CSU a considerable amount of money, and to get an early look at and use of Primo Central.

Scope

Development of code in Xerxes to integrate Primo Central results.  Early access to and training for Primo Central collection registration.